Factory License Rajasthan
Prerequisite
Pollution license from the Rajasthan Pollution Board
Documents required for registration:
Firm/company ownership documents
- Latest List of Partners/Latest List of Directors/Order of the Managing Agent appointed by Central Government/State Government/Local Authority as an occupier.
- In case of change of directors, submit Form No. 32 of the Companies Act, 1956.
- Partnership deed / Memorandum of Articles of Association.
Land ownership document
- Land ownership documents (sale deed/rent deed/lease deed) with land use conversion document if applicable.
Documents related to electrical power and date of start of production
- Load the sanction copy & the first electricity bill for registration.
Identification document
- Photo ID and proof of address of the occupier.
- Photo ID and address proof of the factory manager.
The process to apply for a factory license in the state of Rajasthan:
Apply for a factory license in Rajasthan
|
STEP 1:
|
For applying for a factory license, register yourself on the website http://www.rajfab.rajasthan.gov.in/
|
|
STEP 2:
|
Register yourself and create your login.
|
|
STEP 3:
|
You have to log in first on Single Sign On and then select the RajFAB icon in the Single Sign-On Dashboard to use the RajFAB application.
Please note that the Business Registration Number (BRN) from http://br.raj.nic.in and the Labour Identification Number (LIN) from https://shramsuvidha.gov.in/home are needed to use the RajFAB web application.
|
|
STEP 4:
|
Keep scanned documents available. Click here to download Form No. 2 (Every page of the documents submitted along with the form should be self-attested by the occupier or the factory manager along with the date.) Enter the web application at www.rajfab.rajasthan.gov.in.
|
|
STEP 5:
|
Click the button. (under the Registration Section for Registration/under the Amendment Section for Amendment)
|
|
STEP 6:
|
Fill in all mandatory fields marked as *
|
|
STEP 7:
|
Make an online payment.
|
|
STEP 8:
|
Submit the application.
|
The time limit for approval
- Non-Hazardous and Non-Power Factories—7 days
- Non-Hazardous Factories—15 days
- Hazardous Factories—21 days
- Factories carrying out our dangerous operation—21 days